Dai un'occhiata alle news

Nevskaya Ratusha administrative and public center with underground parking, Saint-Petersburg, Russia with the total area of 100 736 sq m

  • The installation of unitized façade with natural stone on 3-8 floors of Administrative building: completed in full on the façades facing Degtarny pereulok, 95% of façade have been installed along Moiseenko St; on the main façade the installation is going ahead.
  • Glazing of the drum area of Administrative building courtyards is 90% completed.
  • In the atrium area of Administrative building the steel support structures of the dome, lift shaft, terrace and TV-studio have been installed in full scope, as well as preliminary drilling works on fixing aluminium framework brackets are being carried out on the dome area.
  • On the facades of Business Center-2 installation of ventilated façade with natural stone has been commenced, insulation fixing is going to completion and installation of louvers is under start-up on the roof engineering floor.
  • On the last top floors of Business Center-3 is running the installation of ventilated façade with natural stone – portals and border elements.

Multifunctional residential area with Trud stadium restore on Mytnaya Str, Moscow with the total area of 61 000 sq m

  • On the balcony area of the high-rises the following installation works are going ahead: on bldgs 3 and 4 enameled glass units have been mounted in full scope; the installation of ventilated façade is in progress; on the roof area of bldg 2 installation of the brackets for building maintenance system is currently going ahead, on bldg 1 the brackets have been fixed in overall.
  • The installation of fire rated spandrel panels and ground floor glazing is currently running on building 6. On the roof area of building 6 the parapets and tracks for BMU are being mounted.

Eurasia Tower, plot 12 Moscow-City MIBC, Moscow, with the total area of 74 000 sq m

  • The installation of unitized transparent façade with natural stone is going ahead on the top residential area of the tower; steel outrigger beams are currently being mounted on 49-50 floors.
  • On the Podium area the installation of insulation, wall brackets and guiding profile of ventilated façade is going ahead, as well the installation of support steel brackets for mullion-transom façade of the gallery.

Nevskaya Ratusha administrative and public center with underground parking, Saint-Petersburg, Russia with the total area of 100 736 sq m


Multifunctional residential area with Trud stadium restore on Mytnaya Str, Moscow with the total area of 61 000 sq m


Eurasia Tower, plot 12 Moscow-City MIBC, Moscow, with the total area of 74 000 sq m



©2012 VELKO
141070, Pionerskaya street, 4
Moscow region, Korolev