Take a look at news
VTB-Arena Park project update
Building 1: Black stone revetment on the 1st and 2nd floor corners. Installed aluminum frame for the entrance on 1.4 façade. Marble revetment on the 5th floor.
Building 2: Stone lamellas are being installed on the 3rd floor and decorative lamellas on the technical floor.
Building 3: Revetment on the colonnade and corners of the 14th floor. Installation of the aluminum entrance frames on 3.2 and 3.3 facades.
Building 4: Finished the preparatory work for stone revetment.
Building 5: Finished the installation of stained glass frame at the entrance. Ongoing preparatory work for stone revetment.
ZIL transport hub update
Finished the elevator shaft revetment.